Start for freeScaling up to volume production is a critical step for manufacturers looking to bring their products to the market at scale. This process involves several key phases, each designed to address different aspects of production readiness. In this article, we explore the transition from tooling, creating work instructions, and setting up the supply chain to the actual building of the product. We delve into the three essential phases known as EVT (Engineering Validation Test), DVT (Design Validation Test), and PVT (Production Verification Test), providing insights into what each phase entails and why they are crucial for a successful scale-up to volume production.
The Phases of Scaling Up to Volume Production
EVT: Engineering Validation Test
The EVT phase marks the first step in the volume production process. This phase is all about assembling the product for the first time by the production team. Building a small number of units initially, this stage is critical for learning and identifying any potential bottlenecks, difficult processes, or the need for new fixtures. The primary goal of the EVT phase is to establish a mass production configuration and a repeatable process that can be scaled.
DVT: Design Validation Test
Following EVT, the DVT phase aims to validate the design through a mass production intent process. This phase involves building a larger quantity of units, typically ranging from 50 to 300, which are then used for various testing requirements such as drop tests, or for submitting for certifications. The DVT is a crucial step in ensuring that the entire assembly process is ready for mass production and meets all the necessary standards and requirements.
PVT: Production Verification Test
The PVT phase is the final step before entering full production. It involves running a significant number of units, often between one thousand to two thousand, to truly test the mass production intent. This phase is vital for verifying that all aspects of the production process are finalized and ready for scaling. Unless any surprises arise during the PVT phase, the product is considered ready for full production.
Why These Phases Matter
Scaling up to volume production is not just about increasing the number of products made but ensuring that each product meets the required quality and consistency standards. The EVT, DVT, and PVT phases allow manufacturers to systematically approach production scaling, addressing potential issues at each stage and ensuring that the final product is ready for the market. By carefully navigating these phases, manufacturers can avoid costly mistakes and delays, ultimately streamlining their path to successful volume production.
In conclusion, understanding and effectively managing the EVT, DVT, and PVT phases are critical for any manufacturer looking to scale up to volume production. Each phase plays a vital role in ensuring that the product can be produced at scale while maintaining high quality and meeting all necessary requirements. As we've seen, transitioning through these phases requires careful planning, testing, and validation, but with the right approach, manufacturers can achieve a smooth transition to full production and bring their products to market successfully.